Greater Shepparton City Council last night endorsed a proposal to use capital works funds rather than take out a loan for the building of the new Shepparton Art Museum with a new estimate of $39.9m for the project.
Two cost reviews during the detailed design phase have revealed that to build to the current budget would result in the new SAM building having limited functionality and requiring further future investment to be operational. The project is consistent with the 2014 business case, competition guidelines and awarded design; there have been no changes to the business case concepts for the project.
The Functional Design Option estimate for the new Shepparton Art Museum project is $39.9m; previous costings were $34.5m. This is an increase of $5.35m. The SAM project was endorsed in May 2015 under the provision that Council would undertake a loan of $10m to fund the project. Financial modelling indicates the project can be funded through existing cash reserves rather than a loan.
Council’s contribution increase to $5.35m in upfront capital would be partially offset by an estimated $4.23m savings in loan interest expense.
The Business Case is four years old and during that period construction costs have risen greater than inflation (4 per cent predicted for this financial year). Environmental systems for art museums are complex and tailored for the building which has increased the project costs.
This is a significant building for Greater Shepparton and in order to have the functionality required for an international standard art museum there is no ability to compromise on design and fit out.
The tender for construction will go out in August 2018 and there is a contingency built into the $39.9m project budget to allow for variations, which is standard practice for any construction project.
While the increase is within accepted parameters for Council, to fund the increase, additional measures to potentially offset this financial risk will be explored such as selected grants for components of the project and changes to the SAM Foundation Capital Works/Trust contribution breakdown.
The 2018/2019 financial year project bid process will not be affected by the SAM capital requirements.
Background information
At the 19 May 2015 Ordinary Council meeting, Council agreed to:
Funding achieved
Successful funding applications from:
Funding in progress
Timelines*
April 2017: Council resolved to appoint Denton Corker Marshal Architects to prepare the necessary detailed design based on the project objectives adopted by Council.
September 2017: SAM site incorporated planning amendment approved
February 2018: Demolition works commence
March 2018: Detail design completed
August 2018: Construction design completed
Late 2018: Build commences
September 2020: Project completion
(*timelines subject to change)
More News from Greater Shepparton
Tuesday 21st of April,
Budget commitment marks progress for Shepparton rail services
Greater Shepparton City Council has welcomed the Victorian Government’s budget commitment to increase train services on the Shepparton line, following sustained advocacy by Council since 2023. Read more
Monday 20th of April,
Massive week of BMX in Greater Shepparton
Greater Shepparton City Council has wrapped up another massive week of sport, with the 2026 GWM BMX Racing National Championships concluding on Saturday 18 April. Read more
Friday 17th of April,
Greater Shepparton secures headline BMX Racing event ahead of Olympic Games
Greater Shepparton City Council is pleased to announce that Shepparton will become the focus of international BMX Racing when it hosts two rounds of the UCI BMX Racing World Cup in 2028. Read more
Wednesday 15th of April,
Council continues targeted engagement ahead of Murray-Darling Basin Plan review
Greater Shepparton City Council is intensifying its advocacy and engagement efforts to ensure local community and industry voices are heard as part of the Murray Darling Basin Plan (MDBP) review, with public submissions closing on 1 May 2026. Read more
Tuesday 14th of April,
Shepparton BMX Multi-Use Events Pavilion named finalist for 2025 Victorian Sport Award
Greater Shepparton City Council is proud to announce that the Shepparton BMX Multi-Use Events Pavilion has been named a finalist in the Local Government Initiative of the Year category at the 2025 Victorian Sport Awards. Read more
Tuesday 14th of April,
New Payble option gives Greater Shepparton residents more flexibility in paying rates
Greater Shepparton City Council has introduced Payble as a new way for residents to pay their rates, providing more choice and flexibility with payments. Read more
See All News
Want to get the latest news and events in your Facebook feed?
Just go to our Facebook page and click the Like button.
More Events in Greater Shepparton
Friday 24th of April,
Puff Walk
Puff Walks are more than just steps – they’re connections. Read more
Tuesday 28th of April,
Rainbow Storytime at Shepparton Library
A wonderful celebration of diversity in children’s picture books. Read more
Tuesday 28th of April,
Shepparton Malayalee Association presents Voice of Vineeth Sreenivasan Live
Vineeth Sreenivasan is not just a name in Indian cinema — he is an emotion, a memory, and a melody that lives within us. View on Riverlinks
Thursday 23rd of April,
Libraries After Dark Board Game Fun at Shepparton Library
It's all fun and GAMES at Libraries After Dark! Read more
Monday 27th of April,
Mighty Movers
Looking for something active for your 2–6‑year‑old? Read more
Sunday 26th of April,
Shepparton Gators - Round 5
Big V Basketball is here!! Get ready for high-energy basketball and show your support for the Women's and Men's Big V Gators. Go GATORS! Read more
See All Events