Marungi Street Drainage Project Update

We are pleased to advise that work to upgrade the stormwater drainage network from the Marungi / Nixon Street intersection through to Knight Street Shepparton is progressing well.

Work has continued north towards Knight Street, with the northbound lane of Marungi Street remaining closed as previously advised. Upon completion of stormwater installation works along northbound Marungi Street towards the end of March, works will then enter Knight Street. Whilst the Knight Street works are situated in the westbound carriageway, the area will be operated under traffic controllers, and no closures are anticipated along Knight Street. This area of works is scheduled for the last week of March.

There have been delays to the progress due to the discovery of unknown services, wet weather and site constraints which has unfortunately extended the project completion until the end of April 2026.

As works approach properties in Marungi Street, the contractor will continue to liaise with residents to discuss how they will be able to access their property during this period. You will notice ongoing changes to parking availability along Marungi Street as works are completed, with some spaces reopening and others temporarily closed as required.

Work to be Undertaken Location of the work and community impact Anticipated timeframe
Stage 1 & 2   COMPLETED
Stage 3
  • Marungi Street northbound from Nixon / Marungi Street roundabout to Knight Street - CLOSED (access to Residents and Business will be maintained)
  • Marungi Street southbound - OPEN
  • Parking will be available via Knight Street entry only

Progressing throughout March

Weekday Hours: 7:00am – 5:00pm

Stage 4
  • Knight Street westbound – OPEN but operated under traffic controllers
  • Marungi Street northbound from Nixon / Marungi Street roundabout to Knight Street - CLOSED
End March
Stage 5
  • Three (3) stormwater connections from central parking to east side Marungi Street
April – traffic details to follow
Stage 6
  • Reinstatement works including asphalting and line marking
April – traffic details to follow

Stage 3 - Traffic Movements

Road users and pedestrians are reminded to observe all on site signage, detours and direction provided by traffic controllers during the works.

Council apologises for any inconvenience this may cause and appreciates your patience throughout the duration of these works.

Additional information in relation to this project can be found on the Greater Shepparton City Council’s Major Projects’ web page, where you can also subscribe for email updates in relation to this project.  Alternatively, contact Council Project Manager Karen Tidd on (03) 5832 9700 or email projects@shepparton.vic.gov.au

 